-
Buckram Road Bridge Replacement
Buckram Road Bridge Replacement
Location: LOCUST VALLEY, NY
PROJECT HIGHLIGHTS / SCOPE OF WORK
-
Single Phase, Design/Build bridge replacement
- Replace existing steel 3-span with single span steel railroad bridge
- Raise track elevation for additional clearance
- Retaining wall installation for new track profile
- Abutment modifications and repairs
PROJECT DESCRIPTION
One mile east of Long Island Rail Road Locust Valley Station stood an ancient structure known as Buckram Road Bridge. Built in 1889, Buckram Road Bridge, 134 ft. in length, carried one track with three spans. Approximately two bridge strikes occurred per year, resulting in cumulative structural damage.
The bridge and adjacent viaduct spans required total replacement. Following an investigation, design of the new roadway alignment addressed hazardous vehicle line of sight angles, minimum roadway clearance requirements of 14 ft.-0 in., lane width, pedestrian accessibility and track alignment.RCC replaced the 128 year-old structure in a single weekend track outage.
The new elevated vertical clearance significantly reduces the probability of bridge strikes and increases safety. The new bridge reduces the number of spans from three to one, resulting in a single-span ballasted deck bridge, ultimately reducing LIRR maintenance costs.
Gallery
-
-
Benjamin Franklin Bridge Patco Track Rehabilitation
Benjamin Franklin Bridge PATCO Track Rehabilitation
Location: PHILADELPHIA, PA TO CAMDEN, NJ
Client: Delaware River Port Authority and Port Authority Transit Corporation
Contract Value: $103,000,000
Project Dates: 2022
PROJECT HIGHLIGHTS / SCOPE OF WORK
- Replaced 120 year old 120’ long steel truss bridge with 324’ long precast concrete bridge
- Extended and realigned roadway traveling over bridge
- Constructed new twelve car pocket track
- Constructed 1,600 LF of new retaining walls
- Installed drainage upgrades including 2,400 LF of below-grade HDPE piping
- Performed sitework
- Received the American Society of Civil Engineers (ASCE) Metropolitan Section 2017 Design/Build Project of the Year Award for recognition of excellence in the successful completion of a major design/build project
PROJECT DESCRIPTIONAt the time of its opening in 1926, the Benjamin Franklin Bridge was the world’s longest suspension bridge, spanning the Delaware River, connecting Philadelphia, PA and Camden, NJ. This $103,000,000 project, executed by joint venture partners Railroad Construction Company, Inc. and Iron Bridge Constructors, involved the rehabilitation of the bridge’s entire track system.
The joint venture introduced and helped implement redesigns to improve construction. The original design suggested construction 80 ft. segments of the track system and support structure and installing temporary rail. After months of careful planning, the design was changes to complete 400 ft. segments at a time and installing permanent rail. No temporary rail was used.
Two outages were scheduled, taking the tracks out of service. A sixty day closure of the south tracks followed by a fifty day closure of the north tracks was required to perform extensive repairs and completely replace the tracks. All existing track was removed enabling the repair and replacement of steel stringers and appurtenances, previously inaccessible under and behind the rail system. New concrete supports were formed and poured. Sand blasting and painting was performed on the newly exposed structural support steel and 120 tons of new steel was installed and painted. Through strong collaboration and coordination of crews and activities between the joint venture, DRPA and PATCO, the north side was completed three days ahead of schedule, earning an incentive payment from DRPA.
The new track system includes over 9,000 new timber ties and two and a half miles of new rail. Eighty signal/electrical enclosures were constructed and more than thirty miles of signal, power and communications cable was laid. The entire electrical system was upgraded and modernized including train signal controls, high voltage wiring, fiber optics and circuits, new conduit and relocated lighting.
The removal and replacement of timber ties presented a challenge but resulted in a new and innovative concept that utilized a portable conveyor system on the bridge, eliminating the bundling of timbers and loading out with heavy equipment. The conveyor method removed timber operations from the critical path and allowed blasting and painting to begin earlier than planned.
These tracks were originally put into service in 1936 and began carrying PATCO trains in 1969. Today, the PATCO Speedline operates twenty-four hours a day and transports over 10,000,000 passengers per year. These much needed improvements enable PATCO and Delaware River Port Authority to provide a safer, more efficient commute for the tens of thousands who use this mass transit system every day.
Uniquely complex and an intricate blend of multiple construction disciplines, DRPA and PATCO consider this project to be a model for future jobs, using a collaborative, goal-specific approach.
“The Ben Franklin Bridge Track Rehab project is a testament to what can be accomplished with an experienced, knowledgeable and safety minded contractor.”
-Mike Venuto
DRPA Chief Engineer
Railway Track & Structures February 2016This project received the 45th Annual American Council of Engineering Companies of New Jersey (ACECNJ) Engineering Excellence award in 2016. The annual Engineering Excellence Awards (EEA) competition recognizes and celebrates engineering achievements that demonstrate the highest degree of skill and ingenuity among firms throughout the state of New Jersey.
Gallery
-
Colonial Road Design/Build Improvement Project
Colonial Road Design/Build Improvement Project
Location: LONG ISLAND, NY
Client: Metropolitan Transportation Authority-Long Island Rail Road
Contract Value: $25 million
Project Dates: 2022
SUMMARY
- Replaced 120 year old 120’ long steel truss bridge with 324’ long precast concrete bridge
- Extended and realigned roadway traveling over bridge
- Constructed new twelve car pocket track
- Constructed 1,600 LF of new retaining walls
- Installed drainage upgrades including 2,400 LF of below-grade HDPE piping
- Performed sitework
- Received the American Society of Civil Engineers (ASCE) Metropolitan Section 2017 Design/Build Project of the Year Award for recognition of excellence in the successful completion of a major design/build project
WHAT MADE THIS JOB COMPLEX
-
Accelerated timeframe with road closure limited to one year
- Restrictions on power shutdowns by PSEG Long Island
- All work to be performed around the train schedule with only limited outages permitted
- Job site in a confined space of a suburban neighborhood causing logistical problems for delivery and staging
PROJECT OVERVIEW
Gallery